World novelty new construction feeder railroad Weglosen

Here we will keep you updated on the replacement construction of the Weglosen feeder railway.

Hoch-Ybrig

Video



Milestones

AUGUST 2022 
The planning approval process has started. We can expect the building permit in around 8 months. 

NOVEMBER 2022 
We have received the good news from the Federal Office of Transport that no objections have been received. 

MAY 2023 
We have received the building permit from the Federal Office of Transport for the new construction of the Weglosen-Seebli 3S cable car. 

JUNE 2023 
The construction work is already in full swing. The first foundation slab has been concreted. 

SEPTEMBER 2023 
The last major concrete stage has been completed. 

JUNE 2024
 The assembly work in the mountain station has mostly been completed. The woodwork will follow. 

Construction work at the valley station is in full swing. The first foundation slab has been concreted.