World novelty new construction feeder railroad Weglosen
Here we will keep you updated on the replacement construction of the Weglosen feeder railway.

Video
Milestones
AUGUST 2022
The planning approval process has started. We can expect the building permit in around 8 months.
NOVEMBER 2022
We have received the good news from the Federal Office of Transport that no objections have been received.
MAY 2023
We have received the building permit from the Federal Office of Transport for the new construction of the Weglosen-Seebli 3S cable car.
JUNE 2023
The construction work is already in full swing. The first foundation slab has been concreted.
SEPTEMBER 2023
The last major concrete stage has been completed.
JUNE 2024
The assembly work in the mountain station has mostly been completed. The woodwork will follow.
Construction work at the valley station is in full swing. The first foundation slab has been concreted.